Hedcor Manolo Fortich Update

April 28, 2016

Hedcor Manolo Fortich Update
HYDRO IN MINDANAO. A renewable energy developer of AboitizPower, Hedcor is on its 42% completion of the Manolo Fortich Hydro 1 and 21% for Manolo Fortich Hydro 2, recorded as to date. Work is focused on the additional excavation for headpond to prevent erosion of the side slope and drilling works for the 6-km tunnel to be used for a portion of water diversion. A 5-km pipeline has laid over 14km target while, the opening of the access road is nearing completion with 28km is already accessible out of 30km. The foundation for weir and desander were continuously concreted to meet the target groundworks.