Commissioning of Unit 2 of Aboitiz coal plant moved back by 10 months

February 24, 2016

THERMA South Inc. (TSI), a subsidiary of Aboitiz Power, said on Tuesday it would have to delay the commissioning of Unit 2 of its 300-megawatt (MW) coal power plant in southern Davao City by 10 months because the facility was damaged during the Mindanao-wide blackout that occurred on April 5.